PVC floor is often used in public places, which has the advantages of waterproof and fireproof. The

2020-05-23

1. Pour the mixed self leveling slurry on the construction floor, it will flow and level the ground by itself. If the design thickness is w4mm, it needs to use the special tooth scraper to scrape slightly.

2. Then, the construction personnel shall put on special spiked shoes, enter the construction ground, use the special self leveling air cylinder to roll gently on the self leveling surface, and let out the air mixed in the mixing to avoid bubble pockmarked surface and interface height difference.

3. Please close the site immediately after the completion of construction, do not walk for 5 hours, avoid heavy object impact within 10 hours, and lay PVC floor after 24 hours.

4. In winter construction, the floor shall be laid 48-72 hours after self leveling construction.

5. If it is necessary to finish polishing the self leveling, it should be carried out after the self leveling cement is completely dry.